Bahia Executive Summary
Since 1977,
Debra Management Company has worked to design a development plan for the Bahia
site that is compatible with the existing community and its residents, while
meeting the requirements of the City of Novato and local, regional, state, and
federal agencies, and addressing the concerns of other interested parties. To
meet these goals the company has also proposed measures to avoid, reduce, and
mitigate environmental impacts identified in three Environmental Impact Reports
(EIRs).
Over the course of 22 years,
the Master Plans submitted by Debra Management have successively reduced the
number of proposed residential units—from 1500 in 1982, to 729 in 1990, and to
424 in 1995 (see Figures 1-5). In each case these reductions have
been made to respond to newly identified concerns. The reductions have removed
proposed homes from peninsulas to avoid wetlands impacts and avoid human
exposure to electric and magnetic fields, and removed proposed homes from
highland areas to reduce tree loss, provide for wildlife movement, and avoid
impacts on airport operations and potential airport impacts to new residents.
In 1994, the City of Novato
directed Debra Management to redesign the project in line with the Mitigated
Project Alternative in the 1994 Certified EIR. As such, the current project is
the environmentally superior alternative, as defined by the City’s own ER
consultants, various commentators on the EIR, and the City itself through both
its Planning Commission and City Council.
The current plan, as
described in the Revised 1995 Master Plan, consists of 424
single-family and townhouse units, as well as a community center complex and
public park.
Beyond direct avoidance of
environmental impact through reduction of the project, Debra Management also
has proposed a number of mitigation measures that offer far greater mitigation
value than legally required or typically seen in similar cases. For example,
for wetlands mitigation, the current plan calls for preservation and dedication
of the entire 333 acres of the Central Lowlands and Western Marsh. In all, 531
of the 650 total acres at the
site—81% of the site—are to be dedicated to open space and deeded to those
entities having most interest in them. In addition, the project proposes to
create 36.5 acres of seasonal marsh on the Twin House Ranch site directly
across the Petaluma River from the project and an additional 33 acres of native
prairie at that site as a buffer habitat to the marsh. For oak woodland
mitigation, the project preserves 196 of 224 acres of woodland on-site and has
proposed to fund off-site planting of native tree species at several open space
areas in the vicinity of Bahia.
The history of Debra
Management’s successive proposals for reduction and mitigation of environmental
impacts represents a determined effort by the developer to be environmentally
sensitive, and to meet the myriad and sometime conflicting requirements of
different agencies and authorities—even as regulations, jurisdictions, and
agency management have changed many times during the course of the development
planning process.
Unfortunately, the history
also reveals an approval process that resembles an endless loop. In each of the
years 1980, 1990, and 1995, the project was revised to respond to the City’s
most recent ER. However, each time, as the developer subsequently sought
approval from regional, state, and federal regulatory agencies having
jurisdiction over the site, and further revised the plan to meet their
requirements, local authorities, in turn, have requited a new ER because the
Plan had been changed. This occurred even though each time the revised Plan
reduced development and associated environmental impacts.
In addition, even as the
project has addressed the environmental issues that have been raised, the terms
and conditions under which the project’s environmental impacts are being
evaluated were changed and new issues raised. In 1995, while the
developer was awaiting approval of its latest Master Plan, the Army Corps of
Engineers determined that new seasonal “emergent wetlands” had formed on
engineered fill on several peninsulas and on a former site of dredged spoils.
These areas (or “putative wetlands”), which cover approximately 14 acres, had
not been designated as wetlands by the Corps in previous determinations in 1983
and 1986.1 As a result of the new determination, the emergent
wetlands required additional study and mitigation.2
Issues that had been
resolved in one compliance cycle have also been re-visited in later EIRs.
Although the loss of oak woodlands had been reduced below the threshold of
significance in the 1995 Master Plan, the 2000 Subsequent
Environmental Impact Report (SEIR) required new mitigation.
Issues related to the
project now include a multitude of biologic, geologic, transportation, and
other land-use concerns (the 2000 SEIR lists 61 separate issues). Studies to
investigate these issues have been conducted for more than 20 years by two
teams of ER consultants employed by the City as well as consultants hired by
the developers, including some of the leading biologists, botanists,
geologists, hydrologists, meteorologists, architects, civil engineers, and
traffic and noise engineers.
Over the years these issues
have been examined and re-examined in extraordinary detail. For example? to
precisely determine the number of trees that might be lost to installation of
roadways and utilities, an actual field count of trees was made in 1994. This
survey plotted 1,628 individual trees by size, location, and species.3 To
determine the presence of, and possible adverse impact on, the Salt Marsh
Harvest Mouse, five separate live trapping surveys were conducted in 1982,
1987, 1991, Spring 1996, and Fall 1996, involving more than 3,000 trap nights.4
This level of survey and scientific research is far beyond what is
normally conducted prior to a Master Plan or a Precise Development Plan.
The result of these studies
is that the Revised 1995 Master Plan and subsequent supplementary proposals
have outlined measures to avoid, reduce, or mitigate the environmental impacts
raised to date in the ER. For example, the following areas have all been
addressed:
• Oak
Woodlands.
The current project reduces tree loss to approximately 2,880 trees, or about
12% of the more the 23,500 trees estimated to exist on the site. This level is
well below the25% threshold of significance used as a rule-of-thumb by the
California Department of Fish and Game.5 At the same time, more than
196 of 224 acres of oak woodland will be preserved.
• Wetlands. The Revised 1995 Master Plan calls for
preservation and dedication
of the majority of wetlands, including all 333 acres
of on-site diked salt marsh (Central Lowlands and Western Marsh). In the Plan,
all impacts on tidal wetlands are avoided and overall impacts have been reduced
from 26 acres to 18.5 acres. Proposed mitigation for impacted wetlands includes
creation of 37 acres of seasonal wetlands on the Twin House Ranch site.6
• Rare and Endangered Species. Direct effects on state and
federal-listed species of plants and animals have been avoided. Where indirect
effects are possible, mitigation measures have been proposed. For example,
possible direct effects of the project on the Salt Marsh Harvest Mouse (SMHM)
in the Central Lowlands and Western Marsh have been avoided by elimination of
development in those areas. Extensive mitigation measures have been proposed
for possible indirect effects on the California clapper rail.7
• Wildlife
Movement. Wildlife movement is not expected to be impacted by the planned
development. The Revised 1995 Master
Plan protects the most sensitive habitats (wetlands, diked and tidal marshes,
dense oak woodlands), and protects the avenues, such as draws and canyons,
where local movements by large mammals are likely to occur.8
• Geotechnical Issues. Analysis shows that
geogrid mats used to reinforce slope fills can avoid earthquake-induced damage,
destabilized slopes can be mitigated through avoidance or the use of deepened
spread footings, and construction fills can be added to compensate for settlement.9
• Hydrologic Issues. A storm water drainage system
included in the project is designed to reduce peak runoff flows and reduce the
potential of pollutants to enter the system.10
• Traffic Impacts. The reduced level of
development in the 1995 Plan enables high levels of service on all related
traffic thoroughfares, and in one case the Plan agrees to contribute to
construction of a recommended measure to improve service)11
In
each instance, the issues raised in the EIRs have been studied and solutions
found.
The
development plan has also long had the approval of the majority of current
residents of the Bahia area, as represented by the Bahia Homeowners Association
(BHA). From its earliest plans in the 1980s, the developer has tried to design
a plan acceptable to this community. The 1990 Master Plan included a
navigational lock that would eliminate the need for the continuous dredging of
the lagoon to remove silt and provide the navigational waterways that had been
planned for the Bahia community since its inception. However, due to the
difficulties this portion of the Plan encountered at state, regional, and
federal levels, it was withdrawn from later plans. At present, the BHA is
independently seeking solutions to the community siltation problems.
Nonetheless, the current development plan does demonstrate its continued
commitment to the BRA through a proposal to pay the Association $10,000 per
unit or lot sold, to be applied to Association-sponsored siltation solutions.
The
bottom line is that this project takes into account all of the possible
consequences of development, then resolves them in the manner proposed by
leading experts in each of the relevant disciplines. At the same time, the size
of the development has been reduced dramatically from 2,250 residential units
to 424 units. It has taken some 35 years to reach this point, but Debra
management is now fully prepared to move ahead.