| The 15 acre City maintained Canalways pond has not been dredged since its initial creation in 1973 when its middle was about 6' deep. | |||||||||||||||
| What would it cost to dredge the pond to its origianl depth and ship the silt off site or deposit the fill on site? | |||||||||||||||
| Repair outflow pipe | $ 60,321 | ||||||||||||||
| Drain pond edge draining | $ 7,500 | ||||||||||||||
| Automate pump controls | $ 125,135 | ||||||||||||||
| Corps dredge permit | $ 9,782 | ||||||||||||||
| Total as of 2/99 | $ 202,737 | These figures based on 1999 estimates. | |||||||||||||
| Removal of accumulated pond settlement | |||||||||||||||
| Cubic yards | 72000 | ||||||||||||||
| Cost/yard Redwood | $ 20 | ||||||||||||||
| Cost/yard Canalways | $ 3 | ||||||||||||||
| Removal of 72,000 cubic yards of accumulated pond settlement | |||||||||||||||
| To Redwood Sanitary | $1,440,000 | ||||||||||||||
| To Canalways | $ 216,000 | ||||||||||||||
|
|||||||||||||||