The
15 acre City maintained Canalways pond has not been dredged since its initial
creation in 1973 when its middle was about 6' deep. |
What
would it cost to dredge the pond to its origianl depth and ship the silt off
site or deposit the fill on site? |
|
Repair outflow pipe |
$ 60,321 |
|
Drain pond edge draining |
$ 7,500 |
|
Automate pump controls |
$ 125,135 |
|
Corps dredge permit |
$ 9,782 |
|
Total as of 2/99 |
$
202,737 |
|
These figures based on 1999
estimates. |
|
|
Removal of accumulated pond
settlement |
|
Cubic yards |
72000 |
|
Cost/yard Redwood |
$ 20 |
|
Cost/yard Canalways |
$ 3 |
|
|
|
|
Removal
of 72,000 cubic yards of accumulated pond settlement |
|
To Redwood Sanitary |
$1,440,000 |
|
To Canalways |
$ 216,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|