The 15 acre City maintained Canalways pond has not been dredged since its initial creation in 1973 when its middle was about 6' deep. 
What would it cost to dredge the pond to its origianl depth and ship the silt off site or deposit the fill on site?
Repair outflow pipe  $       60,321
Drain pond edge draining  $        7,500
Automate pump controls  $     125,135
Corps dredge permit  $        9,782
Total as of 2/99  $     202,737 These figures based on 1999 estimates.
Removal of accumulated pond settlement
Cubic yards 72000
Cost/yard Redwood  $             20
Cost/yard Canalways  $               3
Removal of 72,000 cubic yards of accumulated pond settlement
To Redwood Sanitary  $1,440,000
To Canalways  $   216,000